Guide de maintenance
73 vuesHow to Prepare Your PRV Fleet for Annual Recertification
PRVrecertificationASMEAPI 527checklist
Why preparation matters
Most recertification overruns come from missing set-pressure data and inaccessible valves, not from the test itself. A one-hour preparation saves days on site.
Checklist
- Export your asset register with tag numbers, set pressures and last test dates.
- Confirm isolation and drain-down windows for each process unit.
- Clear safe access — scaffolding or lifting plans for elevated valves.
- Nominate one plant contact with authority to approve on-the-spot lapping.
What we bring
Calibrated benches, certified technicians, and digital certificates issued within 3 business days of test completion.