How to Prepare Your PRV Fleet for Annual Recertification

PRVrecertificationASMEAPI 527checklist

Why preparation matters

Most recertification overruns come from missing set-pressure data and inaccessible valves, not from the test itself. A one-hour preparation saves days on site.

Checklist

  1. Export your asset register with tag numbers, set pressures and last test dates.
  2. Confirm isolation and drain-down windows for each process unit.
  3. Clear safe access — scaffolding or lifting plans for elevated valves.
  4. Nominate one plant contact with authority to approve on-the-spot lapping.

What we bring

Calibrated benches, certified technicians, and digital certificates issued within 3 business days of test completion.